PAVING NOTICE
Spring Street, Sand Hill Road
Beginning October 26, 2010
Tuesday, October 26 – Fine grading of Spring Street from Boltwood Avenue to Churchill Street
Wednesday, October 27 – Fine grading of Sand Hill Road from Pine Street to Puffers Circle; pave Mill River Tennis Courts; place binder on Spring Street
Thursday, October 28 – Place binder on Sand Hill Road from Pine Street to Mill River Bridge
The order of construction is subject to change. Call the DPW office at 259-3050 for the latest order of construction.
• Construction work will take place from 6:30 a.m. to 4:00 p.m.
• No parking will be allowed on either side of the street during construction work.
• Detours may be in place and will vary according to construction work. Residents will have driveway access but may experience minor delays.
• Please obey construction signs during all phases of work to insure your safety and the safety of construction crews, and the general public.
If there is inclement weather that prevents construction, the schedule will move to the next day.
PLEASE OBEY CONSTRUCTION SIGNS & TRAFFIC DETAIL OFFICERS
ON-STREET PARKING WILL NOT BE ALLOWED
WHILE CONSTRUCTION CREWS ARE ON-SITE
DRIVE CAREFULLY AROUND CONSTRUCTION CREWS
EXPECT DELAYS AND SEEK ALTERNATE ROUTES IF POSSIBLE
For questions or additional information concerning this project, contact the DPW office at 259-3050, or email the DPW at marshalle@amhersma.gov.
Time of issue: 10/22/2010, 12:00 p.m.
Issued by: Elizabeth Marshall, Engineering
Amherst Department of Public Works