Amherst Woods Construction Update
Curbing Removal and Roadway Reclamation
Starting
Tuesday, September 24th, 2019
7am -5pm
Warner Brothers will be removing the berm, with a milling machine, on Wildflower Drive on Tuesday, September 24th, 2019.
The road will be reclaimed to gravel and graded, Wednesday through Friday.
IMPORTANT NOTE, PRIOR TO MILLING AND RECLAIMING OPERATIONS:
If any resident has sprinkler heads, invisible pet fences, plantings, etc., inside the Town Right of way (up against the back side of the asphalt curb) please clearly mark the location of them. The Town is not responsible for damage to these systems but will try to avoid them if they are marked.
EXPECT POSSIBLE DELAYS & SEEK ALTERNATE ROUTES
ON-STREET PARKING IS PROHIBITED DURING CONSTRUCTION OPERATIONS- VEHICLES WILL BE TOWED
SLOW DOWN IN WORK ZONES
All roads will remain open to local traffic during construction.
Weekly announcements will follow with additional updates and schedule alterations.
For questions or additional information concerning this project contact the Amherst Department of Public Works at 413-259-3050 or at publicworks@amherstma.gov
Time of issue: 9/20/2019, 3:00 PM
Issued by: Jason O. Skeels, P.E.,
Town Engineer,
Department of Public Works
Amherst, MA