Paving and road construction on Pine St and Cowls Rd will continue throughout the week of November 2nd. Please drive carefully around construction crews, obey traffic detail officers and follow construction signs and detours.
Monday, November 2nd –Warner Brothers LLC will complete the installation of asphalt berm on Cowls Rd.
Tuesday, November 3rd – Structures crews will also be raising sewer, water and drainage structures on Cowls Rd.
Wednesday, November 4th - Warner Brothers LLC start the installation of the final coat of asphalt on Pine St.
Thursday, November 5th – Warner Brothers LLC complete the installation of the final coat of asphalt on Pine St.
Friday, November 6th – Warner Brothers LLC start the installation of the final coat of asphalt on Cowls Rd.
Cowls Rd Detour Plan (for Thursday only)– In order to maintain a relatively smooth traffic flow in and out of the road we plan to have ONE WAY traffic flow travelling west from Montague Rd to Sunderland Rd. The Detour plan will remain in effect during until the paving is complete. All traffic is advised to enter Cowls Rd via Montague Rd and exit via Sunderland Rd.
OBEY TRAFFIC DETAIL OFFICERS
FOLLOW CONSTRUCTION SIGNS AND DETOURS
DRIVE CAREFULLY AROUND CONSTRUCTION CREWS
AND EXPECT DELAYS
NO ON-STREET PARKING WILL BE ALLOWED DURING WORKING HOURS
If inclement weather prevents construction, the schedule will move to the next day.
Construction is expected to begin at 6:30am and continue until 5pm or later.
For questions or additional information concerning this project, contact the DPW office at 259-3050, or email the DPW at publicworks@amherstma.gov.