[ARCHIVED] Cowls Road & Pine Street - Revised Construction As Of 10-26-2015

20110427pavingsched.PNG

DAY LOCATION/ACTIVITY

Mon, 10-26 Cowls Road –Grading

Tues, 10-27 Cowls Road - Grading

Weds, 10-28 Cowls Road – Sidewalk construction

Thurs, 10-29 Cowls Road – Sidewalk paving

Fri, 10-30 Pine St – Top course paving

OBEY TRAFFIC DETAIL OFFICERS

FOLLOW CONSTRUCTION SIGNS AND DETOURS

DRIVE CAREFULLY AROUND CONSTRUCTION CREWS
AND EXPECT DELAYS

NO ON-STREET PARKING WILL BE ALLOWED DURING WORKING HOURS

If inclement weather prevents construction, the schedule will move to the next day.
Construction is expected to begin at 6:30am and continue until 5pm or later.

For questions or additional information concerning this project, contact the DPW office at 259-3050, or email the DPW at publicworks@amherstma.gov.