Friday, September 25th - Construction crews will be completing the fine grading on Harkness Rd. and possibly High Point Dr., Overlook Dr. & Juniper Ln. later that day and/or Saturday. (There is a chance that some of this work might occur on Saturday September 26th)
Monday, September 28th - Paving crews will be placing the base coat of hot mix asphalt on Harkness Rd. and possibly Overlook Dr. and/or Juniper Ln.
Construction crews will be completing the fine grading on Highpoint Dr., Overlook Dr. and/or Juniper Ln.
Tuesday & Wednesday, September 29th and 30th -Paving crews will continue to place the base coat of hot mix asphalt on Highpoint Dr., Overlook Dr. and/or Juniper Ln.
Wednesday & Thursday, September 30th and October 1st -Paving crews will place the top coat of hot mix asphalt on Highpoint Dr., Overlook Dr. and/or Juniper Ln.
Friday, October 2nd - Paving crews will be placing the top coat of hot mix asphalt on Harkness Rd.
OBEY TRAFFIC DETAIL OFFICERS
FOLLOW CONSTRUCTION SIGNS AND DETOURS
DRIVE CAREFULLY AROUND CONSTRUCTION CREWS
AND EXPECT DELAYS
If inclement weather prevents construction, the schedule will move to the next day.
Construction is expected to begin at 6:30am and continue until 5pm or later.
For questions or additional information concerning this project, contact the DPW office at 259-3050, or email the DPW at publicworks@amherstma.gov.
Time of issue: 9/22/2015, 9:00 a.m.
Issued by: Jason O. Skeels P.E.
Town Engineer