Amherst Woods Sanitary Sewer Phase 1
Monday June 8th, 2015
WILDFLOWER DRIVE- CLOSED TO THROUGH TRAFFIC
On Monday Revoli will continue extending the last three sewer stubs on Wildflower Dr between Larkspur Dr and Ladyslipper Cir. They anticipate completion of these sewer laterals between 12pm and 2pm at which point the road will be re-opened to through traffic.
Monday June 8th, 2015 Approximately 12:00PM
Tuesday and Wednesday June 9th & 10th, 2015
LADYSLIPPER CIRCLE- CLOSED
On Monday sometime after noon, Revoli will begin extending sewer stubs on Ladyslipper Cir. This will require the complete closure of all vehicular access to Ladyslipper Cir. Vehicular access will be prohibited until they have completed the service stubs. They hope to be finished on Ladyslipper by Wednesday June 10th, 2015.
All vehicles must exit Ladyslipper Cir before noon- 12 pm on Monday and 7am on Tuesday and Wednesday. If you cannot leave before these times please make arrangements to park on Wildflower Dr. Please park a minimum of 100 ft. from the intersection.
Wednesday or Thursday June 10th or 11th, 2015
Work will begin on Larkspur Drive
Depending on when the service laterals are completed on Ladyslipper Circle, Revoli anticipates starting work on Larkspur Drive possibly on Wednesday or Thursday. We will post and hand deliver additional notices next week when we have a better idea of when and where the work will begin.
Additional Testing, Paving, Cleanup and Invert Work will also continue in various locations throughout the week.
We do not anticipate any work on Fridays with the possible exception of the Paving Crews.
For questions or additional information concerning the project please contact the Amherst Department of Public Works at 413-259-3050 or at publicworks@amherstma.gov
Time of issue: 6/5/2015, 10:30 am
Issued by: Jason O. Skeels, P.E., Town Engineer,
Department of Public Works, Amherst, MA