Amherst Woods/Station Road Sewer Extension

Last Updated:  July 5, 2018
  
Current Status:  Geeleher Enterprises will begin installing the  new sewer main and abandoning an existing
water main on Station Rd, between Wildflower Dr and Hawthorn Rd, starting on Monday, June 25
th. Station Rd will remain closed to through traffic during working hours.

Project Information: This project is to extend sanitary sewer to the remainder of Amherst Woods and the eastern end of Station Road.

 

Preliminary Schedule

Tentative Start Date Tentative Completion Date Description of Work
06/14/18 09/28/18 Pump Station Site work and Installation by Public Works crews on Wildflower Dr
06/25/18 06/29/18 Water service relocations on Station Rd
07/02/18 07/13/18 Water Main removal, abandonment, and trench patching on Station Rd
07/16/18 08/24/18 Gravity Sewer Main, Services and trench patching on Station Road
08/27/18 09/21/18 Sewer services, testing, site cleanup and punch list items on Station Rd