Amherst Woods/Station Road Sewer Extension

Last Updated:  March 23, 2018
  
Current Status:  Geeleher Enterprises will begin installing the remaining sewer services on Trillium Way starting Monday, March 26th. This work is expected to last two weeks, during which time the road will be closed from 7:00 am to 5:00 pm.  Residents of Trillium Way are advised to park on Wildflower Dr if they need to access a vehicle or leave later than 7:00 am. Once work begins, there will be no safe way to accommodate vehicular traffic.

Foxglove Lane will also be closed between the dates of March 26th and 28th. This closure will effect houses #16 through #31. Residents may park on the side of Foxglove Ln beyond house #15, allowing room for trucks and equipment to pass.

Upon completion of the installation of the sewer services, trench paving, loam and seeding will begin.  This work is expected to last one week during which vehicular traffic will be allowed. Residents are advised to expect some delays during this time.


  
Project Information: This project is to extend sanitary sewer to the remainder of Amherst Woods and the eastern end of Station Road.

Preliminary Schedule

Tentative Start Date Tentative Completion Date Description of Work
05/15/17 05/19/17 Test holes, site preparation, and silt fence on Wildflower Dr between Indian Pipe Ln and Station Rd.
05/22/17 06/16/17 Sewer main, services, testing and paving on Wildflower between Indian Pipe Ln and Station Rd.
06/19/17 07/19/17 Sewer main, services, testing and paving on Alyssum Ln.
07/19/17 08/11/17 Sewer main, services, testing and paving on Indian Pipe Ln.
08/14/17 08/18/17 Sewer main, services, testing and paving on Wildflower between Indian Pipe Ln and Foxglove Ln.
08/21/17 09/08/17 Sewer main, services, testing and paving on Foxglove Ln.
09/11/17 09/22/17 Sewer main, services, testing and paving on Wildflower between Foxglove Ln and Trillium Ln.
09/25/17 09/27/17 Sewer main, services, testing and paving on Wildflower between Trillium Ln and Larkspur Dr.
09/27/17 10/31/17 Sewer main, services, testing and paving on Trillium Ln.
11/01/17 11/15/17 Site cleanup and punch list items.