Amherst Woods/Station Road Sewer Extension

Last Updated:  September 12, 2018
  
Current Status:  Caracas Construction is raising structures and manholes on Larkspur and Trillium in preparation for berm and final paving.  Once they have completed Larkspur and Trillium, they will move over to Foxglove, Indian Pipe, and Alyssum in order to lower structures in preparation for reclaiming.

Project Information: This project is to extend sanitary sewer to the remainder of Amherst Woods and the eastern end of Station Road. 
 
  

Preliminary Schedule

Tentative Start Date Tentative Completion Date Description of Work
06/14/18 09/28/18 Pump Station Site work and Installation by Public Works crews on Wildflower Dr
06/25/18 06/29/18 Water service relocations on Station Rd
07/02/18 07/13/18 Water Main removal, abandonment, and trench patching on Station Rd
07/16/18 08/24/18 Gravity Sewer Main, Services and trench patching on Station Road
08/27/18 09/21/18 Sewer services, testing, site cleanup and punch list items on Station Rd