Amherst Woods/Station Road Sewer Extension

Last Updated:  June 2, 2017
 
Current Status: Installation of the sewer main is continuing on Wildflower Dr, from Alyssum Ln to Station Rd and is expected to last for four weeks.  This road will be closed from 7 am to 5 pm on work days.  

Project Information: This project is to extend sanitary sewer to the remainder of Amherst Woods and the eastern end of Station Road.

Preliminary Schedule

Tentative Start Date Tentative Completion Date Description of Work
05/15/17 05/19/17 Test holes, site preparation, and silt fence on Wildflower Dr between Indian Pipe Ln and Station Rd.
05/22/17 06/16/17 Sewer main, services, testing and paving on Wildflower between Indian Pipe Ln and Station Rd.
06/19/17 07/19/17 Sewer main, services, testing and paving on Alyssum Ln.
07/19/17 08/11/17 Sewer main, services, testing and paving on Indian Pipe Ln.
08/14/17 08/18/17 Sewer main, services, testing and paving on Wildflower between Indian Pipe Ln and Foxglove Ln.
08/21/17 09/08/17 Sewer main, services, testing and paving on Foxglove Ln.
09/11/17 09/22/17 Sewer main, services, testing and paving on Wildflower between Foxglove Ln and Trillium Ln.
09/25/17 09/27/17 Sewer main, services, testing and paving on Wildflower between Trillium Ln and Larkspur Dr.
09/27/17 10/31/17 Sewer main, services, testing and paving on Trillium Ln.
11/01/17 11/15/17 Site cleanup and punch list items.