Current Status: Phase 2 of this project will be starting May 15th with Geeheler Construction performing test borings on Wildflower Drive.  Equipment will be mobilized to the area at this time, and silt fencing and sedimentation barriers will be put in place.
  
No specific dates have been provided by the contractor for the completion of the Teaberry Ln sidewalk. Work will continue on the sidewalks as crews and equipment become available. 

Project Information: This project is to extend sanitary sewer to the remainder of Amherst Woods and the eastern end of Station Road.

Preliminary Schedule

Tentative Start Date Tentative Completion Date Description of Work
05/15/17 05/19/17 Test holes, site preparation, and silt fence on Wildflower Dr between Indian Pipe Ln and Station Rd.
05/22/17 06/16/17 Sewer main, services, testing and paving on Wildflower between Indian Pipe Ln and Station Rd.
06/19/17 07/19/17 Sewer main, services, testing and paving on Alyssum Ln.
07/19/17 08/11/17 Sewer main, services, testing and paving on Indian Pipe Ln.
08/14/17 08/18/17 Sewer main, services, testing and paving on Wildflower between Indian Pipe Ln and Foxglove Ln.
08/21/17 09/08/17 Sewer main, services, testing and paving on Foxglove Ln.
09/11/17 09/22/17 Sewer main, services, testing and paving on Wildflower between Foxglove Ln and Trillium Ln.
09/25/17 09/27/17 Sewer main, services, testing and paving on Wildflower between Trillium Ln and Larkspur Dr.
09/27/17 10/31/17 Sewer main, services, testing and paving on Trillium Ln.
11/01/17 11/15/17 Site cleanup and punch list items.