Amherst Woods/Station Road Sewer Extension

Last Updated:  December 1, 2017
 
Current Status:  Geeleher Construction has ceased construction for the season as of December 1st, 2017. they will be returning in the Spring in order to complete sewer service extensions on Trilium Way and Foxglove Lane, as well as install underground electrical conduit from Station Rd to the pump station. All equipment will be moved off the roadways during this time.  Any grading, loaming, and seeding will be completed after the work mentioned is done.

Re-start dates will be announced in Spring 2018.
 
Project Information: This project is to extend sanitary sewer to the remainder of Amherst Woods and the eastern end of Station Road.

Preliminary Schedule

Tentative Start Date Tentative Completion Date Description of Work
05/15/17 05/19/17 Test holes, site preparation, and silt fence on Wildflower Dr between Indian Pipe Ln and Station Rd.
05/22/17 06/16/17 Sewer main, services, testing and paving on Wildflower between Indian Pipe Ln and Station Rd.
06/19/17 07/19/17 Sewer main, services, testing and paving on Alyssum Ln.
07/19/17 08/11/17 Sewer main, services, testing and paving on Indian Pipe Ln.
08/14/17 08/18/17 Sewer main, services, testing and paving on Wildflower between Indian Pipe Ln and Foxglove Ln.
08/21/17 09/08/17 Sewer main, services, testing and paving on Foxglove Ln.
09/11/17 09/22/17 Sewer main, services, testing and paving on Wildflower between Foxglove Ln and Trillium Ln.
09/25/17 09/27/17 Sewer main, services, testing and paving on Wildflower between Trillium Ln and Larkspur Dr.
09/27/17 10/31/17 Sewer main, services, testing and paving on Trillium Ln.
11/01/17 11/15/17 Site cleanup and punch list items.